How companies appoint us
Choose the 4D scope around the decision you need to make.
A tender animation, baseline review and recovery study are not the same service. The scope, level of detail and update cycle should match the buyer, deadline and decision.
Tender / bidTender 4D Simulation
Usually appointed by: Bid manager, planning manager or pre-construction director
The contractor or specialist bidder must explain a complex method, show control of logistics or distinguish its proposal before the tender return.
Typical scope: Bid-programme and model review, construction sequence, temporary works and logistics representation, review sessions, final animation and key stills for the written submission or interview.
Award / mobilisationBaseline & Mobilisation Review
Usually appointed by: Project director, planning manager, developer or PMC
The proposed baseline must be tested against the physical project before teams, access routes and work fronts are committed.
Typical scope: Programme-to-model linking, site setup and logistics phases, work-area and handover review, decision log and agreed 4D sequence for mobilisation.
ConstructionConstruction 4D Support
Usually appointed by: Project controls, construction or package team
The team needs a clearer way to coordinate upcoming work, report progress or explain the effect of a change.
Typical scope: Rolling look-ahead simulations, critical-area studies, planned-versus-actual views, progress meeting material and updates tied to agreed status dates.
Delay / recoveryRecovery Option Simulation
Usually appointed by: Project director, planner, contractor, developer or PMC
Several recovery ideas exist, but their effect on access, work fronts, logistics and other trades is not clear.
Typical scope: Targeted option modelling, side-by-side sequence comparison, constraint record and decision-ready visuals. Delay analysis is separate unless expressly appointed.
High-risk packageCritical Sequence Review
Usually appointed by: Main contractor, specialist contractor or design consultancy
A concentrated package—such as complex structure, façade, plantroom, fit-out or themed works—has difficult interfaces or installation constraints.
Typical scope: Focused model preparation, package sequence, access and installation review, interface workshops and a concise output for tender or delivery coordination.